Legrand Junction 69 kV Rebuild

Transmission construction and improvement

Grid light

Montgomery, Alabama

March-April 2024

 

United Utility replaced 27 wood pole structures with concrete during a two-week outage window. Services provided included ROW improvement and support and transmission line construction.